Established in 1970 with volunteer firefighters, the Vadnais Heights Fire Department has evolved over time to meet our community’s changing needs.
The South Fire Station was built in 1993 to support paid on-call firefighters who responded from home or day jobs. In 2010, the North Fire Station was rebuilt as a satellite location during the department’s paid on-call era – helping reduce travel time for firefighters coming from the north side of the city.
As demand grew and the role of firefighters expanded significantly, the department began providing 24-hour duty crew coverage in 2014, starting with weekend shifts and select overnight weekday shifts. Remaining weekday evening shifts were added in phases over the next few years as additional funding became available, with full 24/7/365 coverage achieved in 2019.
To support centralized operations out of the South Fire Station, all emergency response from the North Fire Station ended in 2022, allowing the facility to serve as additional storage space for vehicles and equipment.
Today, full-time fire captains oversee a team of about 40 part-time firefighters, with additional full-time staff responding alongside them during the day. This allows for efficient, cost-effective approach that delivers fast, reliable response while keeping costs well below what a full-career department would require.
-
Over the past two decades, researchers have significantly advanced the profession’s understanding of the long-term health risks firefighters face. Further, training and safety standards, operational expectations and the demands emergency response have all grown.
In the 2010s, national guidance on fire station design began reflecting the growing demands and health impacts of 24/7 emergency response — with a much greater emphasis on cancer prevention, recovery health and long-term wellness.
Modern fire stations support firefighter health, safety and readiness by reducing exposure to harmful contaminants, giving crews dedicated areas to rest and recover between calls, and providing enough space to house and quickly maneuver today’s larger vehicles and equipment.
-
Modern fire apparatus is larger than the trucks the South Fire Station was built to house in 1993 — and for good reason. Today's fire trucks carry significantly more equipment to meet the wide range of emergencies fire departments now respond to, from structure fires to medical calls, vehicle crashes, hazardous materials incidents and technical rescues.
Fire behavior has also changed. Modern building materials and furnishings burn hotter and faster than they did a generation ago. Where firefighters used to have 20–30 minutes before a structure could collapse, today they often have as little as six. That reality demands better-equipped trucks, more advanced tools and larger water and equipment capacity to respond effectively and safely.
Larger apparatus also reflects national safety standards. Today's trucks include enclosed cabs, updated safety systems and space to store gear properly — reducing firefighter exposure to contaminants and improving crew safety on every call. Building a station sized for today's equipment isn't about wanting bigger trucks; it's about being able to house the tools our firefighters need to protect the community.
-
No. VHFD is taking steps to right-size the department to meet the current needs of the community. This includes adjusting the balance of full-time and part-time staff to ensure appropriate staffing levels and maintain a high level of service.
There are no current plans for VHFD to become an exclusively full-time career fire department.
-
Comparing fire departments across communities isn’t as simple as it might seem. Fire departments are organized differently based on the needs of the communities where they operate. Some still use the paid on-call model, where firefighters respond from home or work, while others are full career departments. Some provide ambulance transport and some don't. Some are joint powers organizations serving multiple cities. Lake Johanna, for example, serves three communities. Also, geography matters as much as much as staffing levels. Hugo’s population is close to ours, but because the city covers a much larger area, their department operates very differently.
Vadnais Heights uses a duty crew model and strives to meet National Fire Protection Association (NFPA) and Insurance Services Office (ISO) standards for apparatus staffing. Full-time fire captains provide supervision around the clock, overseeing a roster of roughly 40 to 45 part-time firefighters who carry the majority of the shifts on evenings, overnights and weekends. During the day, full-time staff respond alongside them. It's an efficient approach that provides residents with professional 24/7 coverage at a cost significantly lower than a full career department.
questions about the challenges at the current fire station
-
Built more than 30 years ago, the current fire station has not kept pace with how the VHFD operates today. It was designed for limited on-call use. Over the past 12 years, the city has tried to adapt the station by repurposing rooms, closets and systems. But the building has reached its limits. Key challenges include:
Space constraints. The station is at maximum capacity, with limited room for equipment and staff. In some cases, workspace has been carved out of closets and hallways. The building also lacks proper areas for firefighters to rest, recover and process after difficult calls.
Health and safety risks for firefighters. The building does not properly separate living areas from vehicle bays and gear storage. Firefighters are routinely exposed to diesel exhaust, smoke residue and other harmful contaminants that can impact their long-term health.
Operational inefficiencies. Because there is not enough space, some vehicles and equipment must be stored at the North Fire Station – a satellite facility that is now mainly used for storage. In certain emergencies, crews must first drive to the north station to switch vehicles before heading to a call — adding time when every second counts.
Failing building systems. The HVAC system is outdated and difficult to maintain. Black debris from aging air ducts spreads through the building, plumbing issues leave orange water stains and some sinks are in such poor condition that they are propped up by 2×4’s. These are not minor problems: They reflect systems that are worn out.
-
Before committing to a new station, the City Council wanted a clear answer to one question: would renovating the existing building actually solve the department's problems, or just delay them?
To find out, the city took a hard look at what renovation would really involve. Turns out, it means gutting the building down to the exterior walls, rerouting all the utilities and rebuilding much of the roof, which is essentially a full teardown-and-rebuild on the inside, just keeping the old shell.
In Fall 2025, the city compared two options: renovating the old station or building a new one. The city looked at cost, how each option would affect day-to-day operations and long-term value. The two cost estimates weren't calculated the same way. The renovation cost came from an early concept design. The new construction cost was based on similar projects BKV Architects & Terra Construction had already designed and built. The comparison wasn't exact, but it gave the Council a solid starting point.
At that time, renovation was estimated to cost only $3–6 million less than building new. But renovating an aging, heavily used building also carries real uncertainty. Costs often can't be fully known until walls and ceilings are opened up, which can mean unexpected expenses that extend well beyond what was originally budgeted.
That's when the City Council reached its conclusion: renovation wasn't worth it. Here's why:
It doesn't solve the real problem. Renovation still wouldn't meet the department's current operational needs or leave room for future growth. Space shortages would remain, along with health and safety concerns and other limitations.
Renovation creates its own disruption. The department would need a temporary home during construction, adding cost and potentially slowing emergency response.
It's a short-term fix. Even after all that work, the department would likely need another major investment within a decade.
The cost gap has likely narrowed. As the city finalized the new station's design, its cost estimate rose to reflect the specific building systems and materials selected. We haven't completed a renovation design, so we don't know its exact cost. But that same process, refining materials and construction costs as the design is finalized, would reasonably push up the renovation estimate, too.
Taken together, renovation just didn't offer the long-term value, functionality or operational improvements needed to justify that scale of investment.
-
Many firefighters today work shifts across multiple departments to build a full-time career, and they naturally gravitate toward stations that support their health, safety and well-being. When a facility exposes crews to contaminants, lacks space to recover between calls or doesn't reflect modern fire service standards, it becomes harder to attract and keep experienced firefighters — and easier for them to commit to serving somewhere else.
That has real costs for the community. Recruiting and training new firefighters takes significant time and resources, and every experienced firefighter who leaves takes years of hard-earned knowledge with them. Residents benefit most when experienced, well-trained crews are the ones responding to their emergencies.
Expectations, training standards and liability in fire service have all grown significantly over the past two decades. Providing firefighters with a facility that supports today's demands isn't a perk — it's essential to maintaining the level of service Vadnais Heights residents rely on.
-
A new, modern fire station would be built to support how the Fire Department operates today, supporting its 24/7 duty crew model and giving firefighters the space, tools and layout they need to respond quickly and safely. This would help improve firefighter retention and recruitment in a challenging hiring environment where many crews take shifts for departments across the metro area.
-
The North Fire Station was built as a satellite facility to support an older staffing model where paid on-call firefighters responded from home or work.
Beginning with the transition to the duty-crew model in 2014, the City gradually shifted emergency response operations to the South Fire Station. Its centralized location, along with its proximity to major roads and regional highways, provided strategic advantages for responding quickly throughout the community. As the duty-crew model evolved, it was in 2022 that the South Station became the City’s sole base for emergency response - with crews living and working in the building 24/7.
Today, the North Fire Station, (now the North Service Center) is mainly used for additional vehicle and equipment storage because the South Fire Station doesn't have enough space.
Shifting full-time operations to this location wouldn't solve these challenges. It would require significant investment to convert the building for 24/7 use, and it isn't positioned to serve the entire community as efficiently as the South Fire Station's location.
Additionally, to have operations out of both North and South Stations, the need to expand staffing increases cost of operations. Given the South Station’s location, it is the optimal choice to operate out of.
-
Joining another fire department in a neighboring city to avoid the cost of a new station is another option that was considered.
The reality is that joining another department wouldn't solve the underlying challenge. Vadnais Heights sits in the middle of surrounding communities, so a fire station in our city would still be needed to maintain fast, reliable emergency response for our residents. And the current South Fire Station falls short of the standards any modern fire department — ours or a partner's — would need to operate safely and efficiently.
Beyond that, the Vadnais Heights Fire Department is a source of pride for our community. Our firefighters know our neighborhoods, our streets and our residents. Maintaining our own department means keeping local control over how fire and emergency services are delivered — and preserving the strong connection between our firefighters and the community they serve.
questions about the Fire Station Project
-
In June 2026, City Council rescinded its preliminary approval of the financing plan for a new fire station. As a result, no bonds were issued, no taxes are being collected for the project and no final construction approval has been granted.
The Council took that step to allow more time for community engagement and education before making future decisions. Since then, the city has continued to focus on providing residents with reliable information about the condition of the current fire stations, the needs of today's fire department and the options available to address those challenges.
That effort includes a project website, community outreach activities, public meetings and the formation of a new Fire Station Advisory Panel. Together, these efforts are intended to help residents better understand the information developed over the past several years and provide additional opportunities to ask questions, share feedback and engage in the discussion.
The condition of the South Fire Station and the need to address its challenges have not changed. What has changed is the city's commitment to spending more time helping residents understand those challenges and the options available.
-
City leaders have been studying its facilities needs and challenges for more than three years. This has been a thorough process that has included building assessments, cost estimates, evaluation of renovation and replacement options, input from fire department leaders and outside experts, and more than 20 public meetings where residents could ask questions and share feedback.
-
Every year we wait, the problem gets more expensive to solve — and the challenges at the current station continue to affect firefighters every day. Construction costs are rising 5–7% each year and have climbed roughly 50% over the past five years. Delaying the project doesn't make it more affordable; it makes it harder to deliver the same project for the same investment.
At the same time, maintenance on the current station has been deferred to avoid putting significant dollars into a building the city plans to replace. If a new station doesn't move forward, critical repairs will still be needed — costing taxpayers more without solving the underlying problems.
Meanwhile, firefighters continue working in a facility that falls short of what they need to stay healthy, safe and ready to respond when every second counts.
-
Possibly. Future construction costs, interest rates and economic conditions are impossible to predict with great certainty. Waiting could lower costs, but it could also make the project more expensive. What we do know is that construction costs, particularly labor and materials, have been increasing faster than the general rate of inflation in recent years. If that trend continues, the same project would likely cost substantially more in the future.
The City's challenge is balancing what it knows today about the condition of the fire stations with what no one can know about future economic conditions. Like many communities across Minnesota, Vadnais Heights is facing difficult decisions about aging facilities at a time when construction costs have risen significantly. The City Council must weigh the potential risks and benefits of acting now versus waiting, while considering community feedback, technical information, long-term facility needs and the potential consequences of delaying improvements.
-
In June 2026, the City Council voted to rescind its preliminary approval of the CIP (Capital Improvement Plan) and bond issuance for the project to recommence the public engagement process.
This action does not mean the city has stopped planning for the future of its fire facilities. Rather, it reflects the Council's desire to re-engage the community before considering the next steps. Years of study have identified significant challenges with the existing Fire Station and evaluated how different options could address the needs of a modern fire department and a growing community. The city wants residents to understand those findings, ask questions, and share their perspectives as the future of the facility is determined.
-
The city is focused on re-engaging residents and community members while providing clear, factual information about the proposed plan. This will include:
Sharing more details about the condition and limitations of the current station.
Explaining the fire department's staffing model in-depth, as VHFD is made up of a combination of part-time and full-time staff.
Presenting detailed cost estimates and financing options.
Creating more opportunities for residents to ask questions and share feedback before future decisions are made.
-
Residents have several ways to ask questions, share ideas and stay involved:
Email or call City Council members
Email or call city staff
Attend City Council meetings and workshops
Speak during public comment or public hearing portions of meetings when available
Attend Planning Commission and Health and Public Safety Commission meetings when the fire station is on the agenda
Attend Fire Station Advisory Panel meetings
Submit questions and comments through the project website – saferfasterreadyvh.com
The application period for the Fire Station Advisory Panel has closed, and panel members are being selected. All panel meetings will be open to the public.
-
The panel will meet four times between October and November:
· October 12: Fire operations presentation and facility tours of the North and South Stations
· October 26: Remodel versus new construction options
· November 9: Financial discussion and financing large construction projects
· November 30: Final recommendation to City Council and wrap-up discussion
The panel is intended to give residents an in-depth look at the condition of the fire station facilities, the operational needs behind them and the options and costs involved in addressing them.
All meetings are open to the public. Residents are welcome to attend and observe the discussion. Audience members will not participate in the panel's formal discussion, but there will be opportunities after each meeting for informal conversations with panel members and city staff.
-
The Fire Station Advisory Panel is a group of residents who will spend several weeks learning about the condition of the city's fire stations, the operational needs of today's fire department and the options available to address those needs.
The panel is designed to give a group of residents an opportunity to take a deeper dive into the issue, ask questions and better understand the challenges, options and tradeoffs involved. Panel members will hear from city staff, firefighters and subject matter experts, ask questions, review information and share their perspectives with City Council at the conclusion of the process.
The goal is to help residents better understand the issue, provide City Council with additional community perspectives and support informed decision-making moving forward.
-
We were very encouraged by the number of residents who applied and the level of interest in serving on the panel. In fact, there were more qualified applicants than available seats, and we're grateful to everyone who was willing to volunteer their time.
Councilmembers Goebel and Moynagh reviewed all applications and selected 13 individuals who they believe will bring a broad range of perspectives, experiences and expertise to the discussion.
The goal was to create a panel that reflects the community, is willing to dig into the information, ask good questions and help City Council better understand how residents view the challenges and options facing the city.
-
The city has taken several steps to control costs and make sure any investment provides long-term value for taxpayers:
· Renovation was studied seriously. The city spent more than two years evaluating whether the existing building could be renovated instead of replaced. The options were compared based on cost, impact on fire operations and long-term value. That work found that renovation would cost nearly as much as a new station while addressing only some of the building’s problems. A new station was identified as the better long-term value because it would fully support today’s fire operations, address health and safety concerns and provide room to meet future needs.
· The city hired a Construction Manager at Risk. Terra Construction was brought into the process early to provide more reliable cost information, identify possible savings and help manage financial risk as the design developed.
The city authorized early bidding on precast concrete. This was intended to secure pricing for a major part of the building before construction costs increased further.
The proposed construction plan would have kept the fire department operating from the current station. This would have avoided the cost and disruption of temporarily relocating fire operations. Renovating the existing station would likely require the department to operate elsewhere during construction and could potentially impact emergency response.
A new station could help address two city facility needs. Some fire equipment is currently stored at the North Station because the South Station does not have enough space. Bringing fire operations together at a new South Station could allow the North Station to be used by Public Works, which also needs more space. That could help the city avoid or delay the cost of expanding or building another Public Works facility.
It is also important to explain that City Council rescinded its preliminary bond approval in June. No bonds were issued. The scope, cost and financing of any future project remain open for further review.
The need for a long-term solution to the facility’s serious deficiencies has not gone away. The city is taking more time to help residents understand the condition of the current station, the needs of today’s fire service and why the earlier analysis identified a new station as the best long-term value.
-
Over the past three years, the city has invested approximately $1 million in planning and development work to understand its facility needs and address the widespread challenges its current facilities create for the Vadnais Heights Fire Department. Those costs include architectural and engineering services, surveying, legal support, public engagement and communications, and other professional services needed to evaluate options, develop plans and prepare the project for future decision-making. This level of investment is typical for a project of this size and complexity.
Before considering a significant public investment, City Council and staff determined it was important to fully understand the condition of the existing facility, evaluate alternatives, develop reliable cost estimates and engage residents in the discussion. The planning work completed to date has helped the city carefully assess its options, refine potential solutions and provide residents with accurate information before any final funding decisions are made.
Planning and evaluation costs are intended to be incorporated into the project's overall financial terms with an initial reimbursement of those costs from the bond proceeds.
-
Financing allows the city to spread the cost of a long-term asset over many years, much like a home mortgage. For that reason, financing is commonly used by cities across Minnesota when investing in major public facilities, such as fire stations, that are expected to serve residents for generations.
The city's capital planning process strives to balance community needs with responsible financial management. Financing can help reduce the year-to-year impact on taxpayers by paying for the facility over an extended period of time. That means future residents who benefit from the station will also help share in the cost of the investment.
-
If we chose to save for the Fire Station rather than finance the project, the timeline would depend on how much we set aside each year.
For example, if we started by saving $100,000 per year and increased the annual savings by $100,000 each year, it would take approximately 24 years to accumulate enough funds. If we started at $200,000 per year and increased the annual savings by $200,000 each year, it would take approximately 17 years.
Saving in advance would eliminate the interest expense associated with borrowing. However, it also means that residents would be contributing to a project for many years before the project is actually built. Some residents who contribute during those years may not ultimately benefit from the Fire Station, particularly if they move out of the community before the project is completed.
-
The challenge is that a project of this size is difficult to pay for upfront without delaying needed improvements or placing a much larger burden on taxpayers in a shorter period of time. Financing spreads the cost over many years and allows future residents who will use and benefit from the station to share in the investment.
The city will also look for ways to reduce borrowing costs when opportunities arise. That could include refinancing if interest rates improve or paying down debt more quickly when financially feasible.
-
No. Property taxes are not currently being collected for a new fire station.
In June 2026, the City Council rescinded its preliminary approval of the financing plan and associated bond issuance. As a result, there is no financing in place today and no tax impact associated with the project.
If the Council decides to move forward in the future, a financing plan would need to be approved before any tax impact could occur. Property owners would see that information in a future Truth in Taxation notice and have an opportunity to participate in the public hearing process before taxes are collected.
-
The City Council determined that residents needed more information about the condition of the fire stations, the options under consideration, and the potential costs and impacts of different solutions. Like many cities, Vadnais Heights has limited staff capacity dedicated to public communications and community engagement.
To support this effort, the City hired Rapp Strategies, a Minnesota-based firm that specializes in helping local governments communicate about major infrastructure, public safety and facility projects. The firm serves as an extension of City staff, providing additional capacity and specialized expertise much like cities often rely on outside engineering, legal, planning or information technology professionals.
Rapp Strategies' role is not to advocate for a particular outcome. Instead, its job is to help the City provide accurate information, clearly explain the facts, options and decisions under consideration, answer questions and create opportunities for residents to stay informed and involved.
The City also wanted to help residents better understand the decisions involved in making long-term investments in public safety, community well-being and quality of life. Projects like fire stations require communities to balance costs, service needs, facility conditions and long-term financial responsibility.
Rapp Strategies has served in similar roles for communities of all sizes across Minnesota, including cities such as Maple Grove, Maplewood, Roseville, Hibbing, Dilworth and Litchfield. In each case, the firm's role has been to help residents understand complex projects, get fact-based answers to their questions and stay informed about the choices facing their community.